Where Arctic AI infrastructure is likely to get built

By Brittany Hamilton | Resolution Consulting, LLC | November 24, 2026

A ten-hectare industrial site in southern Finland tells me more about where Arctic AI infrastructure is going than a map of the Arctic does. At Mikkeli, a developer has a long lease, a building permit and a site near existing power infrastructure. Those are three reasons to take the project seriously. The next question is how much power can reach the first data hall, on what date, and at whose expense if the schedule slips.

My view is that the next wave of investment will concentrate in a handful of industrial and utility hubs. Some will be in the Arctic itself. Others will be farther south, where power networks, fiber and industrial sites are already in place. International partners will help build both. The investments I’d take most seriously are the ones where the local utility can deliver power in stages and a customer is ready to pay for the first phase.

Mikkeli shows what an existing industrial site buys you

Aurora Core Technology, the Finnish subsidiary of Nasdaq-listed 3 E Network Technology Group, secured a 30-year lease on roughly ten hectares in the Pellosniemi industrial area. The City of Mikkeli said in April that the building permit had become legally binding. Existing grid infrastructure helped make the site attractive. The company subsequently reported a 9,000 kVA distribution agreement and targeted full energization in 2027, according to Fjord Journal’s project reporting. I’d treat that date as the company’s target and verify the utility’s delivery obligations before putting it into a base case. City of Mikkeli · 3 E Network’s annual filing · Fjord Journal

Mikkeli is in southern Finland. Its relevance to the Arctic is the siting decision. An existing industrial area gives a developer a place to start and a local counterpart that understands the site. I’d still ask how much of the connection translates into usable IT load after cooling and other facility needs, and how much additional capacity the utility can deliver if the customer wants to expand. Land can be cheap while the second grid connection is expensive.

Finland also offers a practical example of how the local economics can improve. Fortum began operating heat pumps at two Microsoft data center sites in May 2026, initially using ambient air as a heat source alongside electric boilers. Server heat is expected to come in as the data centers are commissioned. I’d give recovered heat value in a project model once a nearby buyer can say how much it can take through the year and who pays for the connection. Fortum

Narvik and Alaska show two ways to build inside the Arctic Circle

At Kvandal near Narvik, the milestone I’d pay attention to is the customer contract. Aker says Microsoft contracted the site’s full capacity in the first quarter of 2026. OpenAI was the originally intended anchor under the Stargate Norway announcement. In September, contractor CTS Nordics said construction was underway and put completion of its expanded 100 MW scope in 2027. That gives investors a named customer and a construction schedule to track. I’d still want the power delivery dates for each phase, especially before assuming another campus nearby can secure comparable capacity. Aker shareholder letter · CTS Nordics construction update

On Alaska’s North Slope, STAK is trying to make a market for local gas by building the customer’s power supply on site. On November 10, Alaska’s Department of Natural Resources approved offering a 50-year lease on about 715 acres south of Deadhorse. The proposal calls for 1–3 GW of on-site gas-fired generation, with air-cooled computing facilities and fiber connections. Northern Alaska Environmental Center reports a 15-year gas agreement with ExxonMobil Alaska Production. The campus still depends on delivering the gas, securing air and wetlands permits and building the links that would let customers use the capacity. I’d want to see the first phase sized against signed compute demand before assigning value to the 3 GW buildout. Alaska DNR final decision · Alaska Public Media · Northern Alaska Environmental Center

The North Slope case also puts local costs and benefits into focus. The developer estimates up to 1,500 workers at peak construction and 50–150 permanent jobs. I’d weigh those separately and ask what commitments will be in place when construction crews leave. The state’s decision records concerns about caribou habitat and access for subsistence users, alongside measures such as limiting construction during calving. Those commitments matter to the design and schedule, as do the costs of managing emissions from on-site generation. Alaska Public Media · Alaska DNR final decision

Central Asia is testing what happens when power and compute are developed together

In Uzbekistan, Japan’s Muroosystems, Uzatom and the Ministry of Digital Technologies announced cooperation on a data center designed to draw roughly 50 MW from small modular reactors. The figure describes proposed demand. The agreement puts the electricity source and the data center in the same development plan, with delivery dependent on a future power project. Muroosystems · Uzatom

In Turkmenistan, Muroosystems signed a nonbinding agreement with the Ministry of Energy in May 2026 to explore distributed computing power centers. The company’s separate Chon-Kemin small-hydropower work in Kyrgyzstan gives a useful comparison. Muroosystems describes a roadmap and a power purchase agreement for the plant, which is intended to support the Kyrgyz power system. The disclosed Kyrgyz project is hydropower. The disclosed Turkmen project is a computing proposal. Muroosystems on Turkmenistan · Muroosystems on Kyrgyzstan

What I’d take from these projects for the Arctic is the way the parties are approaching power. A compute customer can give a new generation project a large, dependable buyer if it signs for capacity and has the balance sheet to honor the contract. An energy partner can give a data center a credible path to expansion. Developing the two together also ties up capital on both sides. If the power project slips, the compute operator may have a building it can’t use. If the operator slips, the generator needs another buyer or a contract that covers the delay. I’d settle that exposure before either side orders long-lead equipment.

Japan, South Korea and China are coming at this from different directions

Japan has the clearest project-level link to Arctic connectivity in this set. Japan’s ARTERIA Networks, Finland’s Cinia and Alaska’s Far North Digital formed the development company behind Far North Fiber, a proposed cable linking Japan and Europe via the Northwest Passage. The investment case is that a physically independent route could give carriers and large customers a second way to move traffic between markets. I’d want to see who buys capacity, where the cable lands and how repairs would work before crediting that route to a specific data center. Muroosystems’ Central Asian work shows a separate potential contribution from Japanese firms in engineering and power development. ARTERIA Networks · Far North Fiber

South Korea has a commercial model worth watching. SK Group’s 15-year arrangement with AWS in Ulsan pairs a Korean developer with a U.S. cloud operator in a phased AI infrastructure project. Seoul also has a separate Arctic maritime agenda. The overlap makes Korean groups worth watching as potential equipment, engineering or operating partners. I’d look for a named northern site and a contract before counting Korean participation in an Arctic data center pipeline. Ulsan tells us what these companies can build together in Korea. SK Group · Korea’s Ministry of Oceans and Fisheries

China presents a more immediate ownership question. China’s Arctic policy sets out a broad interest in Polar Silk Road connectivity. Mikkeli gives us a specific commercial case to examine. Trade reporting describes Aurora Core as China-backed, and 3 E’s filing documents the group’s operating presence in Hong Kong. The project is in Finland and should be evaluated on its own ownership and operating arrangements. For infrastructure like this, I’d want to know who ultimately controls the project, who can access or administer customer systems, and what investment reviews or technology restrictions could affect the schedule. Resolving those questions early helps a developer know which customers it can realistically serve. China’s Arctic policy · Data Center Dynamics · European Commission

Where I’d look for the next investment

Cold air can reduce some cooling costs, and access to hydropower can improve the economics where the grid has room. I’d start with two kinds of opportunity. The first is an existing industrial site where a utility can serve a modest first phase and add capacity as customers sign. The second is the infrastructure that can serve several sites, especially independent fiber routes and grid upgrades that have users beyond one campus. In more remote markets, a signed customer with a workload that can tolerate distance matters even more. The cost of building and maintaining a second link has to make sense against that customer’s contract.

The next signals I’d watch are a utility confirming capacity and an energization date, a customer committing to pay for that capacity, and a fiber provider able to show that its backup route avoids the same failure points as the first. In the Arctic, I’d also want the local agreement early enough to affect the design, including who funds upgrades, what the host community gets, and how Indigenous rights and consultation are addressed where applicable.

A multinational deal can give a northern site access to more customers, capital and engineering capacity. I’d put a higher value on the deal that gets the first data hall powered, connected and paid for on schedule. Once that happens, there’s a much better basis for underwriting the second.